Design Survey
August 2011
Utility Identification
Public Involvement Meeting I
November 22, 2011
Utility Coordination
December 2011
Public Involvement Meeting 2
January 27, 2012
Environmental Documentation
March 2012
Public Informational Meeting 3
Project Design
August 2012
Permits
Mn/DOT Final Review
October 2012
Project Letting
January 2013
Public Informational Meeting 4
April 2013
Begin Construction (after Syttende Mai)
May 2013
Project Complete
October 2013