Spring Grove Main Street Reconstruction Project Spring Grove Main Street Reconstruction Project

Home       Project Information       Public Participation       Technical Committee       Schedule       Contact

Email Project Contact

Schedule

Estimated Project Timeline

Design Survey

August 2011

Utility Identification

August 2011

Public Involvement Meeting I

November 22, 2011

Utility Coordination

December 2011

Public Involvement Meeting 2

January 27, 2012

Environmental Documentation

March 2012

Public Informational Meeting 3

March 2012

Project Design

August 2012

Permits

August 2012

Mn/DOT Final Review

October 2012

Project Letting

January 2013

Public Informational Meeting 4

April 2013

Begin Construction (after Syttende Mai)

May 2013

Project Complete

October 2013

 